JOB BOM Process
The Job Bill of Material (BOM)
This process allows one to produce a BOM resultant item using a job, thereby accurately controlling the cost of the resultant item including and labour cost that are applicable.
The Process is as follows:
1.Quote
2.Manage Job
3.Add any labour or service costs
4.Process Job BOM and close
.png)
Resultant Item Setup
Go to Inventory > Configuration
1.Click Add
2.Enter an Item Code. Bear in mind to keep consistent with the current coding convention of your inventory setup.
3.Enter the item description required
4.Ensure the correct Group code is selected
5.Click Save
6.Click the Bill of Material tab
.png)
1.Tick the BOM Item Box
2.Click Save and Close
.png)
Setup the BOM item
Go to setup the Bill of Materials item
.png)
Capture Quote
Job Costing > Activity >Quotation
Enter the GST Production account code
Enter the Description and Reference
Enter an Order number
Click the Address Tab
.png)
Enter the required Division
Enter the required Region
Enter the required Invoice Group if applicable
.png)
Click Save
Click the Add tab
Select the Stock code or description for the resultant item to be produced.
Enter the required quantity
Enter the estimated Cost price
Do not enter a selling price
.png)
Click Save and close
Click the Approval Options dropdown
Select Customer Approval – Remember this must be selected to report correctly.
Select Approve to Job
.png)
Once approve to Job, this screen comes up
Ensure that the ticks based on how you want to control the job
.png)
Ensure the exceed quantities and Value boxes are ticked.
This enables one to exceed quantities budgeted on the job.
Click Continue
Click OK
.png)
Manage Job
Job Costing > Activity > Manage Job
Enter the Job Number
Highlight the required Production Job
Click Manage Job
Click the Cost to Company Button
.png)
Enter the item code of the stock item being used to produce this BOM Item.
Enter the required quantity
Click Save and New to add another item
.png)
Continue to add the items required to produce then resultant item.
.png)
One can check the stock on hand of these items as well as the Resultant item by going to Inventory module > Analysis > Stock Enquiry
.png)
Manage the stock items added to the Job
Double click the line and enter the quantity used.
.png)
When all stock items have been managed. Verify that the job lines are correct and correctly managed.
.png)
Ensure all time sheets from the various staff members have been submitted for capture or have been captured.
.png)
Check the costing analysis of the job
Open the Job
Click the Print Tab
Click the Job Total Analysis Button
.png)
Click the Managed Totals tab
.png)
Click the View Details Button
.png)
Review the details and ensure that all is correct
Once you are satisfied that all lines are correct and the job can now be completed,
Close all the windows and go back to the job search screen
Search for the job, click the Extras dropdown and click the Job BOM Button.
.png)
Enter the resultant item code
Enter the quantity being produced
Click Save
And then click Process
.png)
.png)
Verify the BOM Item Stock
.png)
You will notice that the resultant item stock on hand has now increased accordingly.
.png)