Purchase Order Overview

Video training manual 2016 - Click Here

Overall process

 

The Purchase Order process can run in multiple options from simple steps to multiple steps dependent on how the company wants to run the system:

Below are the various options:

Option 1GRV process

The quickest and easiest route to get stock into the system and update the supplier.  Skips all the steps. 

Has two basic steps:  Create GRV (Preparation) and Process (Complete)

Option 2PO to GRV

Create a Purchase Order, Authorise and Order.

When ordering, option to go directly to GRV. 

Skips Receive Stock and Delivery note.

Option 3PO with authorise to GRV

Create a Purchase Order, request authorisation

When authorised by manager, email sent to say authorised.

Find Purchase Order and click on Order.

When ordering, option to go directly to GRV. 

Skips Receive Stock and Delivery note.

Option 4PO to Receive stock (All) to GRV









 

 

 


Purchase Order Flow Summary

The following steps are taken to ensure that all purchases from the company goes through the Creditors Module.

1 Create the purchase order
2 Ensure all the supplier details are correct
3 Select the correct item call Ledger custom item
4 Scan an attach the original supplier invoice
5 Send for approval
6 The manager receives an email to approve a specific purchase order
7 Manager to go into Webatar App and find the necessary purchase order for approval
8 The manager checks the supplier invoice and how the purchase invoice is captured
9 The manager approves the purchase order
10 At this stage an email will be sent back to the originator who sent the purchase order for approval, that the purchase order has been approved
11 The capture then pushes the purchase order to receive stock and sends the approved purchase order to the supplier
12 Upon Receipt of the goods or invoice, the goods or invoices checked that the values were the same as the purchase order.
13 The clerk will then Confirm all and push the purchase invoice to a goods receive voucher.
14

An email will be sent to the accounts Department, where they will be notified that hey goods received voucher document is ready to be processed to the system.

15 The purchase invoice from the supplier is checked for the final time and then processed into the system.